Implementation Timeline & Delivery Milestones
Accelerated delivery plan ending May 30th, 2026
| Phase | Dates | Focus | Key Deliverables |
|---|---|---|---|
| Phase 1: Engagement & Growth | May 1 - May 7 | Referral engine, UI incentives, and social community hooks | Referral v2, Tutorial UI, WhatsApp/Telegram integration |
| Phase 2: Social & Squads | May 8 - May 14 | Virel Squads Core, Leaderboards, and Campaign Batching | Squad Formation, Points Logic, Weekly Leaderboards |
| Phase 3: Finance & Security | May 15 - May 21 | Withdrawal engines, Admin alerts, and Anti-Spam safety | Withdrawal Rule Engine, Admin Alerts, Liveness Checks |
| Phase 4: AI Hybrid Systems | May 22 - May 30 | Multi-stage AI Verification & Final Launch Hardening | Sharp, TensorFlow Similarity, OpenAI Vision Integration |
Detailed task list and technical milestones
| Week | Tasks & Activities | Milestone Goal |
|---|---|---|
| Week 1 |
|
Growth & UX Foundation Ready |
| Week 2 |
|
Social & SQUADS MVP Live |
| Week 3 |
|
Financial & Security Audit Ready |
| Week 4 |
|
V2 PLATFORM LAUNCH (May 30) |
Gate 1: May 7
Referral systems and onboarding UX must be fully operational on staging.
Gate 2: May 14
SQUADS system and social API integrations verified with real users.
Gate 3: May 21
Financial rules and anti-spam heuristics signed off for production.